2024-2025 City of Venus Planning Submittal Information
City of Venus, Texas
Planning and Zoning
Submittal and Processing Schedule-2024-2025
Application Submission Deadline | Administrative Completeness Check Date
| Staff Review Comments to Applicant | Public Notice (if required)* | Revisions and Responses Due back from Applicant | P&Z packet sent out | P&Z meeting | City Council Meeting |
1/16/2024 | 1/23/2024 | 1/28/2024 | 1/30/2024 | 2/13/2024 | 2/14/2024 | 2/22/2024 | 3/11/2024 |
2/20/2024 | 2/28/2024 | 3/10/2024 | 3/12/2024 | 3/19/2024 | 3/20/2024 | 3/28/2024 | 4/8/2024 |
3/19/2024 | 3/22/2024 | 4/1/2024 | 4/8/2024 | 4/15/2024 | 4/17/2024 | 4/25/2024 | 5/13/2024 |
4/16/2024 | 4/25/2024 | 5/7/2024 | 5/10/2024 | 5/21/2024 | 5/15/2024 | 5/23/2024 | 6/10/2024 |
5/21/2024 | 5/29/2024 | 6/10/2024 | 6/12/2024 | 6/14/2024 | 6/19/2024 | 6/27/2024 | 7/8/2024 |
6/18/2024 | 6/27/2024 | 7/1/2024 | 7/3/2024 | 7/12/2024 | 7/17/2024 | 7/25/2024 | 8/12/2024 |
7/16/2024 | 7/22/2024 | 7/29/2024 | 7/31/2024 | 8/7/2024 | 8/14/2024 | 8/22/2024 | 9/9/2024 |
8/20/2024 | 8/26/2024 | 9/3/2024 | 9/5/2024 | 9/12/2024 | 9/18/2024 | 9/26/2024 | 10/14/2024 |
9/17/2024 | 9/24/2024 | 10/1/2024 | 10/4/2024 | 10/8/2024 | 10/16/2024 | 10/24/2024 | 11/11/2024 |
10/15/2024 | 10/21/2024 | 10/29/2024 | 11/1/2024 | 11/11/2024 | 11/20/2024 | 11/28/2024 | 12/9/2024 |
11/19/2024 | 11/28/2024 | 12/9/2024 | 12/12/2024 | 12/14/2024 | 12/18/2024 | 12/26/2024 | 1/13/2025 |
12/17/2024 | 12/25/2024 | 12/29/2024 | 1/3/2025 | 1/10/2025 | 1/15/2025 | 1/23/2025 | 2/10/2025 |
1/21/2025 | 1/29/2025 | 2/5/2025 | 2/8/2025 | 2/13/2025 | 2/19/2025 | 2/27/2025 | 3/10/2025 |
2/17/2025 | 2/25/2025 | 3/5/2024 | 3/7/2025 | 3/10/2025 | 3/19/2025 | 3/27/2025 | 4/14/2025 |
3/18/2025 | 3/28/2025 | 4/4/2025 | 4/6/2025 | 4/8/2025 | 4/16/2025 | 4/24/2025 | 5/12/2025 |
4/15/2025 | 4/25/2025 | 5/2/2025 | 5/4/2025 | 5/7/2025 | 5/14/2025 | 5/22/2025 | 6/9/2025 |
5/20/2025 | 5/26/2024 | 5/30/2025 | 6/3/2025 | 6/6/2025 | 6/18/2025 | 6/26/2025 | 7/14/2025 |
6/17/2025 | 6/23/2025 | 6/30/2025 | 7/7/2025 | 7/11/2025 | 7/16/2025 | 7/24/2025 | 8/11/2025 |
7/15/2025 | 7/21/2025 | 7/30/2025 | 8/1/2025 | 8/11/2025 | 8/20/2025 | 8/28/2025 | 9/8/2025 |
8/19/2025 | 8/27/2025 | 9/3/2025 | 9/5/2025 | 9/10/2025 | 9/17/2025 | 9/25/2025 | 10/13/2025 |
9/16/2025 | 9/22/2025 | 9/30/2025 | 10/2/2025 | 10/8/2025 | 10/15/2025 | 10/23/2025 | 11/10/2025 |
10/21/2025 | 10/27/2025 | 11/3/2025 | 11/5/2025 | 11/11/2025 | 11/19/2025 | 11/27/2025 | 12/8/2025 |
11/18/2025 | 11/24/2025 | 12/1/2025 | 12/3/2025 | 12/10/2025 | 12/17/2025 | 12/25/2025 | 1/12/2026 |
12/16/2025 | 12/22/2025 | 12/30/2025 | 1/1/2026 | 1/6/2026 | 1/14/2026 | 1/22/2026 | 2/9/2026 |
1/20/2026 | 1/26/2026 | 2/3/2025 | 2/5/2026 | 2/11/2026 | 2/18/2026 | 2/26/2026 | 3/9/2026 |
2/17/2026 | 2/23/2026 | 3/3/2026 | 3/5/2026 | 3/10/2026 | 3/18/2026 | 3/26/2026 | 4/13/202 |
All dates may be adjusted because of rescheduled meetings or cancelations.
A Preliminary Application Conference (PAC) Meeting is required prior to the submittal date to understand the submittal requirements to avoid rejection for having an incomplete application.
*Notices need to be sent to newspaper one week prior to publication.
The following items must be received no later than 3:00pm on the application submittal date (see above) and are required in order to be deemed a complete submittal. If the application is deemed incomplete, a letter and/or email will be provided to the applicant and/or agent no later than 3 business days following the initial submittal date.
Engineering Plan Review Checklist
Attachment | Size |
---|---|
2024-2025 Submittal Schedule | 449.08 KB |